• ATS Le Grandiose Phase 1 - Builder Case is with NCLT and IRP order is issued

Hi

I booked a flat in ATS Le grandiose Phase 1 in august 2015. Now the project is almost ready but some creditor filed with NCLT against the builder. The IRP order is issued and the builder has again started taking payments and making flats ready.

Now my question is, builder is asking for complete payment. Whereas as per the allotment letter, builder should pay 5 rs per square feet amount per month for the number of months of delay. Can I force the builder to adjust the same in final payment? If yes, how. Please guide.
Asked 4 months ago in Property Law
Religion: Hindu

2 answers received in 10 minutes.

Lawyers are available now to answer your questions.

11 Answers

You can request builder to adjust balance payment against compensation payable by builder for delay in delivery of possession 

 

2) if he refuses make full payment and take possession of flat 

 

3) then sue builder to recover compensation amount  for delay in delivery of possession 

Ajay Sethi
Advocate, Mumbai
94746 Answers
7540 Consultations

5.0 on 5.0

What is mentioned in IRP order ?

 

If its mentioned that builder has to pay Rs5 per sq ft as penalty for delay in giving possession of flats. Then I can to support of the order and ask builder to compensate between the penalty amount and final amount.

Ganesh Kadam
Advocate, Pune
12930 Answers
255 Consultations

4.9 on 5.0

Dear client,

Sorry to hear about your situation. The Real Estate (Regulation and Development) Act, 2016 (RERA) governs real estate transactions. RERA Section 18 addresses the right to damages for possession delays.

  1. Examine All Documents: To comprehend the terms and conditions pertaining to reimbursement for delays, thoroughly go over your allocation letter, builder-buyer agreement, and other pertinent documents
  2. RERA Complaint: The RERA authority of the relevant state may receive a complaint from you. RERA Section 18 gives buyers the right to reimbursement for possession delays. The authority may order the builder to reimburse customers for any delays in accordance with the conditions specified in the contract.
  3. Negotiation: You should think about bargaining with the builder before pursuing legal action. Citing the provisions in the allotment letter, make your case and voice your displeasure with the delay. Sometimes, builders could be open to talking things over and coming up with a compromise.

Hope this helps you.

Anik Miu
Advocate, Bangalore
8901 Answers
110 Consultations

4.7 on 5.0

Yes, in terms of agreement you can ask for adjustment or payment. 

Siddharth Srivastava
Advocate, Delhi
1246 Answers

5.0 on 5.0

Your understanding is correct ask builder to adjust 

 

if he refuse you can file complaint against builder before consumer forum and seek orders to direct builder to pay compensation for delayed delivery of possession 

Ajay Sethi
Advocate, Mumbai
94746 Answers
7540 Consultations

5.0 on 5.0

You have not mentioned if the builder has delayed the possession of property after completing the constructions. 

If there is a delay to hand over possession then you are entitled to payment for delay, therefore you can inform the builder in writing to adjust the payment from your side out of the amount he has to pay, but make sure that you do not delay the payment from your side because he may charge penalty for the delay in making the payments.

 

T Kalaiselvan
Advocate, Vellore
84948 Answers
2198 Consultations

5.0 on 5.0

Since the matter is pending against the builder  before NCLT, the RERA may not entertain the complaint, however there is nothing to prevent you from making the complaint in person by filing it physically.

If you do not want to go through the legal process then you can demand the builder to adjust the payments out of the penalty he has to pay due to the delay in completion beyond the stipulated date.

If he still adamantly refuses to adjust and demands the payments from you then you may approach the consumer forum for deficiency in service and unfair trade practice too.

T Kalaiselvan
Advocate, Vellore
84948 Answers
2198 Consultations

5.0 on 5.0

You can file in rera or consumer court the complaint against builder and seem compensation 

Prashant Nayak
Advocate, Mumbai
31954 Answers
179 Consultations

4.1 on 5.0

once the builder company has been admitted to the CIRP the management of the company is taken up by the IRP appointed by NCLT

So the builder cannot raise any demand now from you as the management of the builder is with the IRP

As regards the penalty the builder agreed to pay to you in the allotment letter, you will have to file a claim with the IRP 

if the date for filing claims has lapsed, then you will have to file an application to the NCLT for a direction to the IRP to accept and admit your claim

 

Yusuf Rampurawala
Advocate, Mumbai
7516 Answers
79 Consultations

5.0 on 5.0

Dear client,

In Uttar Pradesh has anything to do with NCLT proceedings, you might have to contact the relevant courts. Force majeure clauses usually protect against unanticipated occurrences, therefore the penalty may vary depending on the details of your agreement. Talk to the builder about changing the penalties and stressing the specific situations. Consider delivering a legal notice outlining the conditions of the agreement and possible legal action if the builder refuses to cooperate. After the NCLT situation is settled, you can file a complaint with the Real Estate Regulatory Authority (RERA) if the problem continues. The RERA Act's Section 18 addresses complaint filing. Seek legal counsel to learn about your rights under the agreement and applicable provisions, such as RERA Section 18(1)(a), in order to pursue redress.

 

Hope this helps you.

Anik Miu
Advocate, Bangalore
8901 Answers
110 Consultations

4.7 on 5.0

- As per law, a builder cannot demand more amount than that was fixed at the time of booking the flat. 

- Further, the Supreme Court, held that term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder.

- Further, held that incorporation of one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the builder

- Hence, the builder cannot ask you more payment on any grounds which was not agreed by you at the time of booking the flat. 

- You can file a complaint before the Consumer forum against the builder 

Mohammed Shahzad
Advocate, Delhi
13246 Answers
198 Consultations

5.0 on 5.0