• Should I go for RERA or NCLT or NCRDC

Hi
I had booked a Flat under " construction linked payment plan" with Vatika Builder at Gurgaon. I have paid ~ 90% of the property value as per the construction linked payment plan.I have paid on time all the demands raised by the builder and as on data there is no demand raised and no outstanding to be paid . I have paid around 1.5 crore.As per the builder buyer agreement signed in Nov'2012 the flat was supposed to be handed over within 3 years ie by Dec' 2015. thus the project is running late by > 3 years and is likely to completed in 1 year or so

I want to have refund of the entire amount, but there is no exit clause in the agreement.I have taken a home loan and purchased another property now. However,the liability of the builder as per the agreement is Rs 5/sqft/month for the delay that is very less.
I have sent a written notice via registered AD ( email too) , to which the builder is not answering. What are the options available with me as I don't want the possession even if the builder offers the same due to inordinate delay and want to have refund with interest. Should i go for NCLT or NCDRC. The project is RERA registered. To reiterate builder will raise the demands in next 5-6 months and likely to offer possession by Dec'2019
Asked 7 years ago in Property Law
Religion: Other

First answer received in 10 minutes.

Lawyers are available now to answer your questions.

9 Answers

Sir you should file a compalint before the RERA authority seeking cancellation and.complete refund of amount along interest due to delay by the builder.

Or alternatively NCDRC can be approached with the same prayer for seeking cancellation and refund due to long delay and further praying for compensation for deficiency in services.

  • Puneet Malhotra v. Parvsnath Developers - Consumer Complaint No. 232 OF 2014. Dated 29th January, 2015

Facts: An agreement for purchase of property dated 28.12.2007 was executed between the Mr. Puneet Malhotra, hereinafter referred to as the ‘Complainant’) and Parvsnath Developer (hereinafter referred to as the ‘Builder’), wherein the Complainant opted for down payment plan, whereby only 5% of the sale consideration remained to be paid at the time of offer of possession.

The construction was to be completed by December 2010, however the same was stopped by the Builder in July 2008 and had not been completed till the day of the decision. Aggrieved by the actions of the Builder, the Complainant approached the Commission, seeking refund of amounts paid along with an interest of 18% to 24% per annum. It was argued by the Builder that the quantum of compensation as mentioned under agreement should be the maximum compensation payable by the Builder in the prevailing circumstances, and not what the Complainant seeks.

Held: The Commission held that compensation mentioned under the Agreement shall be payable only if the possession of the property was accepted by the Complainant, despite the delay.

Compensation Paid: The Builder was ordered to refund the amount deposited by the Complainant, along with interest @ 18% per annum from the date the deposit was made till the date on which the refund was made. Since the rate of interest granted included compensation, no separate compensation or litigation costs were granted.

In my view consumer commission will be better forum to get appropriate remedy in your case.

Shubham Jhajharia
Advocate, Ahmedabad
25513 Answers
179 Consultations

The best recourse right now as to approach NCLT by way of insolvency petition against builder which is the fastest and most effective in case of builder-buyer dispute.

 

NCLT will grant you interest from the payment  till the actual realisation of the debt along with compensation for the mental harassment and agony suffered by you.

 

Consumer court would take the maximum time to get your money back as cases take years to be disposed off in them.

Siddharth Jain
Advocate, New Delhi
6617 Answers
102 Consultations

You should file application before RERA seek refund of your money paid with interest on account of inordinate delay in delivery of possession 

Ajay Sethi
Advocate, Mumbai
99775 Answers
8145 Consultations

1. Thus is common dispute nowadays among the buyers and the developers which run into troubled waters causing inordinate delay in completion of the project.

2. Since there is a dispute going to NCLT under Insolvency Code is not a remedy which would give you any result.

3. On the contrary file case before the NCDRC and seek refund of money along with interest and damages and compensation. 

Devajyoti Barman
Advocate, Kolkata
23653 Answers
537 Consultations

Please go to Rera

Very quick relief 

Plz claim full refund with taxes

You will also be paid interest and compensation for delay on all amounts so far paid

Interest awarded is very high ie 10.05%

Compensation is extra

Consumer forum is useless

Rera is best for faster relief

Yusuf Rampurawala
Advocate, Mumbai
7899 Answers
79 Consultations

Hi, it is advisable to file a complaint under section 18  of RERA , for seeking compensation and interest over your deposited amount .. The RERA , is a fast track forum under which the order is pronounced within 2 months of filing the case as per the provisions  of act ..Since the RERA has a overriding effect , therefore the clauses of the BBA shall be overruled by RERA , under which you can seek interest at rate of 10.75 percent on the amount deposited to the builder

Hemant Chaudhary
Advocate, Gurgaon
4632 Answers
67 Consultations

Once you have sent a notice communicating your decision to cancel the booking and demanded full refund with interest which was not replied nor complied by the builder you approach either RERA or consumer forum for relief and remedy.

 

T Kalaiselvan
Advocate, Vellore
89977 Answers
2492 Consultations

Dear Client, 

Best and fast recovery is RERA, consumer complain is best approch for compendation but time consuming. Nclt not required at present as project is underway and no actual embazzlment of your invested amount.

Penalty will impose acc. To RERa rules. 

Yogendra Singh Rajawat
Advocate, Jaipur
23079 Answers
31 Consultations

You are legally entitled to approach the consumer forum within stipulated time period for grant of refund and compensation etc. That apart from aforesaid remedy you are also entitled to sought your remedy under the new enactment of real estate law as well as you can prosecute the builder under various other law of land.

Mohammed Mujeeb
Advocate, Hyderabad
19325 Answers
32 Consultations

Ask a Lawyer

Get legal answers from lawyers in 1 hour. It's quick, easy, and anonymous!
  Ask a lawyer