1) what are terms of your agreement with builder ?
2) if as per your contract payment is payable slab wise then builder will demand payment form you .
3) forward to builder letter received from Bank wherein bank has categorically refused to disburse funds as no commencement certificate received for 18 th floor
4) request builder to wait for payment till CC is available for 18th floor