• Property Title, Redevelopment & Impact of recovery suit on Redevelopment

We have a Cessed property in Mumbai City. In 1981 (building was 2 Floor building) my late grandmother went into agreement with one developer who was given FSI rights to extend building up to 5th Floor with top floor (5th Floor for us) Unfortunately the developer cheated us with money as well not completing the flat hence recovery suit was filed in 1983. In 1989 court gave us to take possession of incomplete flat (left halfway) and mentioned in the order to recover based on outcome of recovery suit filed in 1983, The case is still going on.
QUESTION: NEW DEVELOPER wants that NOC from the OLD Developer for redevelopment Is it Valid? (Agreement with OLD DEVELOPER did not give land rights / property right except for FSI for extension) Also NEW DEVELOPER wants separate document mentioning that PROPERTY TITLE SUBJECT TO ONGOING SUIT .IS IT RIGHT STEP any laws /section to insulate us
Asked 10 days ago in Property Law
Religion: Hindu

First answer received in 30 minutes.

Lawyers are available now to answer your questions.

8 Answers

1) Your 1981 agreement only gave the old developer a license to build up to the 5th floor using FSI; it explicitly did not transfer ownership or land title.

 

2) Because the old developer abandoned the project halfway through (leading to the 1983 suit and 1989 court order), they breached the core performance of the contract

 

3) While the old developer technically has no valid legal standing today, Mumbai municipal authorities (BMC) and MHADA may freeze new plans if a prior development agreement is still registered on the property and not formally terminated.

 

4) 

Under Section 52 of the Transfer of Property Act, 1882 ), any transfer or creation of new rights over a property while a lawsuit is active is automatically subject to the final outcome of that court case.

If the new developer builds a new structure and your 1983 recovery suit finally concludes, the court’s order will apply to the property regardless.

 

5) Do not sign a standalone letter acknowledging the title is defective. Instead, include a comprehensive "Litigation History" clause directly inside the main Joint Development Agreement (JDA) or Permanent Alternate Accommodation Agreement (PAAA).

Ajay Sethi
Advocate, Mumbai
101096 Answers
8261 Consultations

NEW DEVELOPER wants that NOC from the OLD Developer for redevelopment Is it Valid? - its been 40 years now. the old developer has already lost his rights. but the new developer would anyway want a noc for the purpose of submission to MHADA and BMC to show that there is no cloud on his title. However, if you approach the old developer to give the noc, obviously he will not give. in that case it will be a deadlock for the new developer. you have to tell him that the old developer already lost his rights to the FSI for extension of the old building and if you still insist for his noc, then i cannot do anything because he is refusing. so you either take the development rights on 'as is where is basis' or find another plot

Also NEW DEVELOPER wants separate document mentioning that PROPERTY TITLE SUBJECT TO ONGOING SUIT .IS IT RIGHT STEP - yes this is valid since the suit is pending. in the event you lose, the new developer's rights would be in jeopardy. 

in the DA that you will execute with the new developer clearly specify that there is a pending suit and if the old developer claims or litigates seeing new construction activity then it will be the responsibility of the new developer to tackle him including all legal expenses and costs and the owner will be indemnified and protected in respect thereof

Yusuf Rampurawala
Advocate, Mumbai
8004 Answers
79 Consultations

A NOC is not legally required for title transfer if rights were limited solely to FSI extension, however the terms of agreement will prevail under such circumstances.Since the 1981 agreement granted only vertical construction/FSI rights (to extend up to the 5th floor) without transferring land title, ownership, or development rights to the underlying land, the old developer retains no right or interest in the real property. New developers typically ask for an NOC simply to avoid potential third-party litigation or injunctions from an old contractor. However, coercing you to fetch an NOC from a defaulting developer (especially one involved in a pending suit) is legally unnecessary.

The request to state that the property title is subject to the ongoing suit is legally accurate and mandatory under Indian Property Law. Under section 52 of TP: act, any transfer, development agreement, or creation of third-party rights over a property while a civil suit is pending in a court of competent jurisdiction is automatically subject to the final outcome/decree of that suit.

Under section 14 of the specific relief act, a development contract for construction that was abandoned and resulted in a recovery suit cannot be specifically enforced by the old developer after a delay of over 40 years.

Section 79A of the Maharashtra Housing and Area Development (MHADA) Act, 1976: Governs redevelopment of cessed buildings. It permits building owners or registered tenant associations to redevelop dilapidated/cessed structures without interference from defaulting past builders.

Draft a Custom Indemnity & Covenant Clause in the New Agreement: Insert an explicit clause stating that the new developer indemnifies you against any financial or legal claims raised by the 1981 developer or their legal heirs. Clarify that the recovery suit of 1983 pertains strictly to monetary recovery/damages owed to you, and does not create any charge or encumbrance in favor of the old developer over the land or property.

T Kalaiselvan
Advocate, Vellore
91304 Answers
2528 Consultations

Conclusion: The new developer's request for an NOC from the old developer lacks a valid legal basis, and you have the right to refuse. However, the request to include a "title subject to ongoing litigation" clause in the document is procedurally sound and does reflect the objective fact that there is a pending lawsuit. Your core legal protection stems from the 1981 agreement, which merely granted FSI development rights and did not transfer land ownership, combined with the Bombay High Court's clear stance against requiring NOCs from defaulting former developers in similar cases.

Regarding the NOC issue: Your 1981 agreement only granted the old developer the right to utilize FSI for construction, without transferring land ownership or property rights. Since the old developer breached the contract and abandoned the project, coupled with the Bombay High Court's ruling in cases such as Municipal Staff Om Satlaj CHS—that municipal authorities cannot insist on an NOC from a former developer facing insolvency or default as a prerequisite for a new developer's redevelopment application, as doing so would improperly delay the redevelopment project—your new developer's demand for an NOC lacks a legal basis.

Regarding the "title subject to litigation" clause: You should avoid signing any independent letter acknowledging that title is defective. A more prudent approach is to incorporate a comprehensive "litigation history" clause directly into the main Joint Development Agreement (JDA) or Permanent Alternate Accommodation Agreement (PAAA), clearly stating the existence and scope of the 1983 recovery lawsuit, thereby avoiding the new developer from unilaterally characterizing your title as "defective" in the future. The legal risk you need to be aware of is that under Section 52 of the Transfer of Property Act, 1882 (doctrine of lis pendens), any new rights created during the pendency of the lawsuit will be subject to the final judgment in that lawsuit, but this is a matter of objective legal effect and does not require you to acknowledge it in a separate document.

Actionable recommendation: Before signing any new document, first have your lawyer formally notify the new developer in writing that the 1981 agreement has been terminated due to the old developer's fundamental breach, and cite the aforementioned High Court precedents to support the position that no NOC is required. Meanwhile, insist on including a comprehensive litigation disclosure clause within the main agreement rather than signing a separate confirmation document.

 

 

Lalit Saxena
Advocate, Sonbhadra
565 Answers

Dear Client,

If the old developer was only granted limited rights to FSI/development in the 1981 agreement, the old developer’s NOC would not be mandatory by virtue of the fact that no ownership interest or any rights have been transferred. It all depends on the agreement and orders issued by courts.

It is quite understandable why the new developer seeks a declaration separate from the contract that the property is still under litigation. The new developer should not be made to believe that the old developer owns the property or that his rights have been waived.

Relevant legal provisions:

  • Section 52, Transfer of Property Act, 1882: Doctrine of lis pendens, subject to the nature of the pending suit.
  • Regulation 33(7), DCPR 2034: Relevant to redevelopment of cessed buildings in Mumbai.

My advice: Have a property lawyer examine the 1981 agreement, 1989 possession order and pending recovery suit before signing anything. Include an express reservation of your rights under the court order and pending litigation, along with suitable indemnity provisions in the new redevelopment agreement. Do not obtain or waive the old developer's rights without establishing whether his contractual rights still subsist.

I hope this answer helps, if you have any further queries please do not hesitate to contact us.

 

Anik Miu
Advocate, Bangalore
11579 Answers
127 Consultations

It’s better you file a suit in civil court for getting the declaration of noc is not given by old developer

Prashant Nayak
Advocate, Mumbai
35417 Answers
257 Consultations

The old developer's NOC is not automatically required merely because he was earlier engaged to develop the property or was given FSI-related rights. The decisive question is whether the 1981 agreement created any subsisting, transferable or enforceable interest in the property, or whether the old developer's rights were subsequently terminated or exhausted.

Equally, the 1989 court order and the pending recovery suit must be examined together. The fact that the order permitted your family to take possession of the incomplete flat does not, by itself, establish that every development right granted to the old developer stood cancelled.

1. Is the old developer's NOC legally mandatory?

There is no general statutory rule requiring an NOC from every former developer before redevelopment. However, the old agreement must be examined to determine whether it granted the developer enforceable development rights, an irrevocable authority, or any continuing interest in the property.

The fact that the agreement did not transfer ownership or land rights is relevant, but it does not automatically mean that all rights granted to the developer were merely personal or have ceased to exist.

In particular, examine:

  • Whether the 1981 agreement was registered.

  • Whether it granted exclusive or irrevocable development rights.

  • Whether the developer exercised those rights or created third-party interests.

  • Whether the 1989 court order terminated, modified or preserved any of those rights.

If the old developer's rights were validly terminated or extinguished, his NOC should not ordinarily be necessary. But that conclusion cannot be reached merely from the description of the agreement.

2. Effect of the pending recovery suit

Section 52 of the Transfer of Property Act, 1882 (doctrine of lis pendens) becomes relevant only if rights in the immovable property are directly and specifically in issue in the pending suit.

If the 1983 suit is purely for recovery of money, Section 52 would not ordinarily apply merely because the dispute arose out of a development agreement.

However, the 1989 order granting possession of the incomplete flat and linking recovery to the outcome of the suit needs careful examination. It may have implications for the parties' respective rights in the property.

3. Should you sign a document stating that the title is subject to the pending suit?

The disclosure of pending litigation is appropriate and should not be avoided. However, the wording of the document is important.

It should clearly record that:

  • The pending suit concerns the dispute arising from the earlier development arrangement.

  • The new developer has been informed of the suit and the relevant court orders.

  • The new development arrangement does not amount to an admission of any subsisting rights of the old developer.

  • The new developer's rights will remain subject to the final outcome of the pending proceedings, to the extent legally applicable.

Avoid signing any declaration that admits the old developer's ownership, continuing development rights or entitlement to consent unless those rights have been legally established.

4. Relevant provisions for cessed-building redevelopment

The redevelopment must also comply with the applicable provisions of the MHADA Act, 1976 and the Development Control and Promotion Regulations, 2034, particularly Regulation 33(7), where applicable.

MHADA has also issued guidelines dated 22 August 2023 dealing specifically with incomplete or stalled redevelopment projects of cessed buildings. Sections 79A and 91A of the MHADA Act are relevant to the framework for dealing with such projects.

The old developer's NOC is not automatically a legal requirement simply because he was the earlier developer. Whether it is necessary depends on the subsisting rights created by the 1981 agreement and the effect of the 1989 court order. The pending suit should be disclosed to the new developer, but the disclosure document must not inadvertently acknowledge rights that your family disputes.

The most important documents to examine are the complete 1981 agreement, the 1989 order and the pleadings and relief claimed in the 1983 suit. Without these, it is not possible to give a conclusive opinion on whether the old developer retains any enforceable rights.

Indu Verma
Advocate, Chandigarh
380 Answers
10 Consultations

Sir/Madam,

It is suggested that there is no need of NOC in the present circumstances, how the facts of ongoing recovery suit may be mentioned in the agreement with new developer.

Ganesh Singh
Advocate, New Delhi
7383 Answers
16 Consultations