Hello,
Please tell the facts in detail.
You two entered into a MoU?
You have completed the government work or some private project?
Please share all the details then only a concrete advise can be rendered.
Regards
We had completed building work of cpwd through main contractor but he has not given payment & now he is not reachable & not lifting the phone call,please suggest what to do.
First answer received in 10 minutes.
Lawyers are available now to answer your questions.
Hello,
Please tell the facts in detail.
You two entered into a MoU?
You have completed the government work or some private project?
Please share all the details then only a concrete advise can be rendered.
Regards
1)issue legal notice to contractor to pay your outstanding dues with interest
2) if he fails to pay file summary suit under order XXXVII of code of civil procedure to recover your dues with interest
Send a legal notice to the main contractor calling upon him to forthwith release your payment.
File a recovery suit in case he fails to comply with the LN.
Its a cpwd contract for staff quarters of NIT building at Raipur. Agreement no.09/EE/RCD/2016-17 CPWD awarded contract in the name of krishna construction,jodhpur.Inturn they had given contract to us,we have no agreement but have approved copy of our quotation.Company is transferring partial payment in our account for the past bills.ONE BUILDING WORK WAS DONE BY US,REMAINING IS STILL UNDER PROGRESS BY SOME OTHER CONTRACTORS.SO CONTRACT IS STILL LIVE, NOT COMPLETED. REQUEST YOU TO PLEASE SUGGEST SOME WAY...
Send a legal notice to them and thereafter you have the remedy of filing a civil suit for recovery of the money from Krishna Construction.
Regards
Once quotation is approved it is binding upon the contractor
2) send him reminders to release payment
3) if he fails to pay act as advised herein above
Sir as an operational creditor serve the demand notice to the company(contractor ) for payment of the debts in 15 days if they fails institute a insolvency petition before the Jurisdictional NCLT. This is most effective and fast way to recover you debts,
Get in touch with the Corporate lawyer to serve the demand notice under the Insolvency and Bankruptcy Code.
Inform the CPWD regarding this misdoing of the main contractor.
Issue a legal notice to the main contractor as already advised.
1) One should have made sub contract regarding this before working with Krishna Construction. Now you can make complaint against him under section 420 of IPC and try to make complaint in consumer forum.
For instance a complaint in the labour court can be filed for non-payment of salary, incentives, severance pay and for any other allowance. A case against an contractor can also be filed before the civil court
You should server legal notice to the contractor to make the entire payment along with interest within 15 days of the receipt of the legal notice.
If he fails to do so, you can file a suit for recovery against him in Civil Court to recover your entire dues.
If after receiving the legal notice the main contractor fails to clear your account you would also have an option of filing an insolvency petition in NCLT as an operational creditor in order to recover your money which would be the fastest way to recover your money as cases are tried in a time bound manner in NCLT.
If you have the evidences for the sub contract and the payment details including any agreement between you and the main contractor, you may first issue a legal demand notice, let it be returned undelivered.
you may lodge a criminal complaint with the police for the offences of breach of trust, cheating etc., obtain an acknowledgment for this complaint.
After that you may file a money recovery suit in the civil court on the basis of all the documentary evidences in your support for this claim.