• Rule governing real estate possession exceeding 36 months

i made booking for a 3BHK with a private builder in feb 11 and made the full payment by may 11. however the pace of work does not seem to be finishing by 36 months. request to suggest some method and advice to deal with the builder.
Asked 3 years ago in Property Law from Jhansi, Uttar Pradesh
Hello,

The agreement between you and the builder governs the time frame for completion of the project. It further governs the penalty applicable in case of delay.

In case there is no such agreement between the parties, check the brochure and see the terms written therein. Depending upon the above you make take civil/criminal or consumer action against the builder.

Regards,
Nishant
Nishant Bora
Advocate, Jodhpur
111 Answers
31 Consultations
5.0 on 5.0

Ask a Lawyer

Get legal answers from top-rated lawyers in 1 hour. It's quick, easy, and anonymous!
Ask a Lawyer

Property Lawyers

T Kalaiselvan
Advocate, Vellore
15283 Answers
139 Consultations
5.0 on 5.0
Ajay Sethi
Advocate, Mumbai
24742 Answers
1327 Consultations
5.0 on 5.0
Ashish Davessar
Advocate, Jaipur
18860 Answers
472 Consultations
5.0 on 5.0
Krishna Kishore Ganguly
Advocate, Kolkata
12722 Answers
262 Consultations
5.0 on 5.0
Devajyoti Barman
Advocate, Kolkata
5854 Answers
63 Consultations
4.9 on 5.0
Atulay Nehra
Advocate, Noida
524 Answers
18 Consultations
4.7 on 5.0
Shivendra Pratap Singh
Advocate, Lucknow
2871 Answers
43 Consultations
4.9 on 5.0
Rajgopalan Sripathi
Advocate, Hyderabad
916 Answers
55 Consultations
5.0 on 5.0
Ajay N S
Advocate, Ernakulam
1947 Answers
19 Consultations
5.0 on 5.0
Thresiamma G. Mathew
Advocate, Mumbai
1323 Answers
89 Consultations
5.0 on 5.0