• Rule governing real estate possession exceeding 36 months

i made booking for a 3BHK with a private builder in feb 11 and made the full payment by may 11. however the pace of work does not seem to be finishing by 36 months. request to suggest some method and advice to deal with the builder.
Asked 3 years ago in Property Law from Jhansi, Uttar Pradesh

The agreement between you and the builder governs the time frame for completion of the project. It further governs the penalty applicable in case of delay.

In case there is no such agreement between the parties, check the brochure and see the terms written therein. Depending upon the above you make take civil/criminal or consumer action against the builder.

Nishant Bora
Advocate, Jodhpur
111 Answers
31 Consultations
5.0 on 5.0

Ask a Lawyer

Get legal answers from top-rated lawyers in 1 hour. It's quick, easy, and anonymous!
Ask a Lawyer

Property Lawyers

Ajay Sethi
Advocate, Mumbai
21872 Answers
1141 Consultations
5.0 on 5.0
T Kalaiselvan
Advocate, Vellore
12840 Answers
120 Consultations
5.0 on 5.0
Ashish Davessar
Advocate, Jaipur
17515 Answers
428 Consultations
5.0 on 5.0
Krishna Kishore Ganguly
Advocate, Kolkata
11382 Answers
210 Consultations
5.0 on 5.0
Devajyoti Barman
Advocate, Kolkata
4630 Answers
48 Consultations
4.9 on 5.0
Rajgopalan Sripathi
Advocate, Hyderabad
828 Answers
36 Consultations
5.0 on 5.0
Shivendra Pratap Singh
Advocate, Lucknow
2635 Answers
38 Consultations
4.9 on 5.0
Ajay N S
Advocate, Ernakulam
1853 Answers
18 Consultations
5.0 on 5.0
Thresiamma G. Mathew
Advocate, Mumbai
1286 Answers
82 Consultations
5.0 on 5.0
S J Mathew
Advocate, Mumbai
1933 Answers
61 Consultations
5.0 on 5.0