changing specific dates while keeping the rest of the deal alive is usually treated as an alteration (addendum), whereas cancelling the old contract and substituting a completely fresh one is novation.
2)
4) If it is an addendum: Even under the 2024 agreement, holding charges are heavily regulated under RERA. Builders can only levy holding charges after they obtain a valid Completion Certificate (CC) / Occupancy Certificate and issue a formal, lawful possession notice—and even then, the rate must be reasonable and strictly in accordance with what was agreed in the contract. Furthermore, since the builder delayed handover by 3 months first, you have a counter-claim for delay interest under Section 18 of RERA.
5) Look at your bank's loan sanction letter to see the exact breakdown of what the ₹20 lakhs was approved for (e.g., whether ₹7.7 lakhs was for the builder and ₹12.3 lakhs was meant for registration/interiors/reimbursement).